25-R-071 Genserve Inc. Emergency Generator Systems Replacement-UpradesRESOLUTION 25-R-071
A RESOLUTION BY THE CITY COUNCIL OF THE CITY OF SCHERTZi
TEXAS AUTHORIZING EXPENDITURES WITH GENSERVE INC. FOR
EMERGENCY GENERATOR SYSTEMS REPLACEMENT AND
UPGRADES PROJECT AT THE EAST LIVE OAK WATER FACILITY
AND OTHER MATTERS IN CONNECTION THEREWITH
WHEREAS, the City Staff has a need to replace and upgrade the emergency generator
system and associated electrical infrastructure at the East Live Oak Water Facility; and
WHEREAS, the East Live Oak Water Facility is critical infrastructure and in the
event of a power failure, an inadequate generator would severely impact the City's
potable water supply; and
WHEREAS, In accordance with TXLGC 252.022, a procurement necessary to
preserve or protect the public health or safety of the municipality's residents is exempt from
competitive bid requirements; and
WHEREAS, Staff recommends GenServe Inc., the City's on -call contractor, and has
determined that they are qualified to perform the work for emergency generator system
replacement and upgrades at the East Live Oak Water Facility.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SCHERTZ, TEXAS THAT:
Section 1. The City Council hereby authorizes expenditures with GenServe, Inc. for
the replacement and upgrade of emergency generator systems at the East Live Oak Water
Facility for $521,516, and a total not -to -exceed amount of$571,000.
Section 2. The recitals contained in the preamble hereof are hereby found to be true, and
such recitals are hereby made a part of this Resolution for all purposes and are adopted as a
part of the judgment and findings of the City Council.
Section 3. All resolutions, or parts thereof, which are in conflict or inconsistent with any
provision of this Resolution are hereby repealed to the extent of such conflict, and the
provisions of this Resolution shall be and remain controlling as to the matters resolved
herein.
Section 4. This Resolution shall be construed and enforced in accordance with the laws
of the State of Texas and the United States of America.
Section 5. If any provision of this Resolution or the application thereof to any person or
circumstance shall be held to be invalid, the remainder of this Resolution and the application
of such provision to other persons and circumstances shall nevertheless be valid, and the
City Council hereby declares that this Resolution would have been enacted without such
invalid provision.
Section 6. It is officially found, determined, and declared that the meeting at which this
Resolution is adopted was open to thepublic and public notice of the time, place, and subject
matter of the public business to be considered at such meeting, including this Resolution,
was given, all as required by Chapter 551, Texas Government Code, as amended.
Section 7. This Resolution shall be in force and effect from and after its final passage,
and it is so resolved.
PASSED AND ADOPTED, this jqk�-day oI . 025.
CITY OF SCHEV XAS
Ral ti ez Mayor
A
Sheila Edmondson, dity Secretary
Exhibit A
East Live Oak Water Plant Generator Upgrade Proposal
Geri: e. ve
To: City of Schertz Proposal # 525RL
Attn: Chris Hernandez Date: 5/30/2025
Reference: Live Oak Water Plant Generator Upgrade
Address: 1055 E Live Oak Rd, Schertz, TX 78154
We are pleased to offer the following proposal for the above project:
SCOPE OF WORK
• Remove and replace Generac 500 kW diesel generator
• Install new Kohler 750 kW diesel generator and 2000 amp automatic transfer switch
• Electrical labor and materials for installation
- Run new feeders from main outside to new ATS
- Install new 75 kVA step down transformer to feed MTS for IN room
- Install new 200A MTS for temporary generator connection point
• Trenching for conduits from ATS to new generator location
• Pour new concrete pad for generator
• Offloading and placement of generator onto pad (crane included)
• Remove fuel from existing generator and disconnect electrical
• Remove and haul off of existing generator as needed
• Initial Diesel Fill of base tank (90% tank capacity)
• Startup, commissioning and warranty registration
• Provide engineered drawings for customer site records
BILL OF MATERIAL
Quantity 1 — Kohler Industrial Diesel Generator
750 kW Standby Rated, 277/480V, 3 phase, 4 wire, 60 Hz
UL2200 certified
PMG Alternator
Critical Silencer — shipped loose
APM603 Digital Controller
-Remote Annunciator
-Remote E-Stop Switch
-Integral thermal overload protection
-2 Input / 5 Output programmable module for remote indication
2000 amp main line circuit breaker —100% rated, LSI
48 Hour / 2520 gallon UL142 subbase diesel tank
Block Heater 120VAC
Starting battery, cables, and battery charger
2 Year System Warranty
Regulated by the Texas Department of Licensing and Regulation, PO Box 12157, Austin, TX 787111-800-803-9202, 512-463-6599 Page 1 of 4
Electrical - TECL 29729
nServe
Quantity 1 — ASCO Automatic Transfer Switch
2000A, 480V, 3 pole, 60 Hz
NEMA 3R enclosure
RS-485 Modbus communications
300 Entry Event Log
In -Phase Monitor
Relay Expansion Module w/ Normal and Emergency available output contacts
Strip heater w/ thermostat
2 Year Warranty
TOTAL PROJECT PRICE: $521,616.00
Notes and Assumptions:
No changes to existing electrical infrastructure included.
Permitting as needed with the city.
No temporary or emergency power available to the plant during installation. Temp power for OF (server) room will
be provided as needed during shutdown period.
Power shutdown to be coordinated with city personnel in advance for most ideal day and time.
Proposal assumes the generator feeder will come straight out from the ATS location running underneath
the transformers to generator location. Generator to be located 20 feet out from transformers. GVEC to
approve final location.
Price does not include any federal, state, or local sales, use, property, TERP, or excise taxes that may be
applicable.
Proposal is valid for 30 days. Pricing includes current tariff charges.
Estimated Lead Time:
Generator - 34-36 weeks
A TS - 24-26 weeks
Project Completion Schedule:
40 weeks from date of order
Acceptance:
Signature
Date
Regulated by the Texas Department of Licensing and Regulation, PO Box 12157, Austin, Tx 787111-800-803-9202, 512-463-6599 Page 2 of 4
Electrical - TECL 29729
r
—0000--
Geri.Serve
COMMERCIAL TERMS AND CONDITIONS
1. Engagement of Services
Once work is authorized by the customer, GenServe is committed to certain "ramp up" expenses, both direct and indirect (i.e., specific training, travel, special
tools, materials, project management, etc.) which are generally priced into the entire scope of the project. If the project is canceled, delayed, terminated or
significantly changed through no fault of GenServe, these expenses will be due and payable to GenServe on a pro-rata basis. Any request for reimbursement
of these expenses will be itemized and defined.
2. Changes to Scope of Work
GenServe will notify the customer if there is a material change to the Scope of Work that will require GenServe to expend more monies than originally
budgeted. The customer agrees to pay GenServe for such expenses plus reasonable profit and overhead if the customer desires to continue under the
changed Scope of Work. A detailed specification was not included with the request for quotation. Equipment and services are limited to this quotation. Any
additional requirements are not included with this quotation. GenServe makes no guarantees regarding the performance of listed equipment in connection
with customer loads. All start up and service calls will be performed by GenServe unless otherwise noted.
3. Exclusions and Assumptions
Exclusions:
• Repairs to existing circuits, wiring, plumbing, landscaping, sprinklers, etc.
Painting on newly installed conduit, boxes or equipment
■ Overtime, after hours or holiday work
• Repairs to existing underground circuits or wiring.
■ Repairs to existing underground utilities, sprinkler systems or damaged landscaping or vegetation
■ Repairs or replacement of any sheetrock (drywall) or painted surfaces.
■ Repairs or replacement of any existing structural components.
■ Repairs of any latent defects of existing wiring.
■ Warranty on any existing wiring, devices or equipment or that supplied by others.
■ This proposal does not include any repairs or modifications to existing circuitry.
■ Cutting or coring of concrete walls or flooring.
■ Trip charges will be added to proposed amount if GenServe is required to suspend work at customer's request.
■ Any charges from Electric provider for service.
■ Any code corrections required by the City Inspector for existing conditions.
Assumptions:
■ Work to be done during regular business hours.
■ Customer to provide access to work area.
■ Pricing assumes existing conduit is in usable condition.
■ Ceilings and walls are free and clear of reasonable obstructions: i.e. fire blocks in walls, concrete and blocks in walls and ceilings.
• Please allow up to one to two weeks for scheduling.
• Trip charges will be added to the proposed amount if GenServe is required to suspend work due to customer's request.
• Reoccurring trips will be charged at $150.00 per hour per additional trip.
• Any time spent waiting, in excess of one half-hour, for access to site will be charged at $150.00 per hour per man.
• Conduit to be surface mounted on concrete walls where necessary.
• Any items located in front of the electrical panels to be relocated by others.
• Customer will provide access to all areas where placement of equipment and devices is necessary. If access is not available when previously
agreed upon, there will be additional charges for lost time.
• Power to certain areas may be interrupted to complete the work.
4. Permits and Taxes
Permits are not included unless specifically noted. Permits, inspection fees, drawings, etc., can be provided by GenServe at an additional cost. Any additional
requirements listed in local codes, general specifications or other sources are not included with this quotation. State and local taxes may not be included in
the proposed price unless specifically noted.
S. GenServe's Employees
The customer agrees that it shall not hire any employee of GenServe who is currently working on a project for the customer, or any employee of GenServe
who has worked on a project for the customer within the last twelve months. The customer further agrees not to hire any former GenServe employee that
performed any work on a project for the customer at any time within the prior twelve months. The customer agrees and understands that this provision is
necessary so that GenServe can protect its investment of time and money in its employees, as well as any confidential or proprietary information known by its
employees
Regulated by the Texas Department of Licensing and Regulation, PO Bax 12157, Austin, Tx 78711 I-800-803-9202, 512-463-6599 Page 3 of 4
Electrical - TECL 29729
enServe
6. Payment Terms
For Cash Sales, GenServe requires a 50% deposit with order, 35% due upon delivery of equipment, balance due upon completion of startup and testing. Late
charge of 1.5% per month on unpaid balance over 30 days. A 20% Cancellation fee will apply (of total quoted price). Pricing is firm for order(s) received
within 30 days of quotation date. A service charge may be charged on all past due amounts. Amounts will be considered past due 30 days after date of
invoice.
7. Warranty
Standard equipment manufacturers warranty applies. AGS will warranty all labor and material on all generator and electrical service work for 2 years. GenServe
will warranty labor and material on workmanship / code compliance indefinitely.
S. Indemnity
Subject to the provisions herein, each Party will maintain commercially reasonable insurance for its respective business activities. Each Party will defend, indemnify
and hold the other Party, their respective officers, directors, shareholders, members, managers, partners, agents, affiliates, employees and independent contractors
harmless from any claims, cost, demands, suits or liability arising out of the indemnifying Party's negligent acts or omissions or the negligent ads or omissions of its
employees, sub -contractors and agents, whether based upon breach of contract, negligence, strict liability or otherwise, arising from or incidental to the services
contemplated under this Agreement; provided, however, that the Party seeking such indemnification shall give the indemnifying Party (i) prompt written
notice of any such claim or threatened claim, and (ii) full cooperation in any defense or settlement of the claim (at the expense of the indemnifying Party).
The foregoing indemnification obligation shall not apply to the extent that such claim is the fault of or is caused by the negligence or willful misconduct of
the Party seeking indemnification, and shall not apply to the extent the cost or damages of the Party seeking indemnification are covered by their own
insurance.
9. Attorney's Fees
If GenServe, LLC is required to hire attorneys to collect amounts owed under this agreement, the customer agrees to reimburse GenServe for all attorneys'
fees, expert fees and other legal expenses that it may incur to collect such amount.
10. Incorporation by Reference
Unless expressly agreed in writing otherwise, these Standard Terms and Conditions are a part of, and hereby incorporate by reference, all Proposals submitted
by GenServe to the customer and any Credit Agreement signed by the customer, and all terms and conditions of any such Proposals or Credit Agreements
11. Tariffs and Import Taxes
If, after the effective date of this agreement, any new or amended tariffs, duties, or import taxes are imposed on materials or components used in the
manufacture of the goods covered by this agreement, GenServe shall have the right to adjust the contract price to reflect the increase in costs directly
attributable to such new or amended tariffs, duties, or taxes, upon providing written notice to [the Buyer] with supporting documentation.
By signing a GenServe proposal, the signatures to this agreement warrant that they have authority to enter into this contract
and that they have read the above Standard Terms and Conditions and agree to abide by them.
Regulated by the Texas Department of Licensing and Regulation, PO Box 12157, Austin, 7X 787111-800-803-9202, 512-463-6599 Page 4 of 4
Electrical - TECL 29729